Timeline

Project Timeline


New

 
DatesProjects
Wednesday, June 26, 2024Prefile Request Filed
Friday, August 9, 2024Draft Resource Reports 1 and 10 FIled
Tuesday, September 10, 2024Open House in Hawthorn, NV at the Hawthorn Convention Center (USO Building) -- noon to 3pm; 5-8pm
Wednesday, September 11, 2024Open House in Fallon, NV at the Comfort Inn. noon to 3pm; 5 to 8pm.
Wednesday, December 4, 2024Scoping Process ends
Friday, July 11, 2025Great Basin Files Section 7(b) and 7(c) application with FERC
Friday, July 10, 2026Requested Date for FERC Order
Saturday, May 1, 2027Anticipated Construction Start Date
Friday, October 1, 2027Target In-Service Date