Monday, November 1, 2027 | Target Project In-Service |
Sunday, October 31, 2027 | Anticipated Construction End Date |
Tuesday, March 2, 2027 | Anticipated Construction Start Date |
Monday, March 1, 2027 | Great Basin Awards Construction Contract |
Sunday, November 1, 2026 | Great Basin will begin to mow the ROW in preparation for construction |
Thursday, October 1, 2026 | Great Basin submits Implementation Plan |
Tuesday, September 29, 2026 | FERC issues Certificate of Public Notice and Necessity for the Project |
Friday, September 18, 2026 | Great Basin submits Implementation Plan |
Friday, September 18, 2026 | Great Basin files to accept the Certificate (157.20 (a)) |
Tuesday, September 1, 2026 | Relocation Design is finalized |
Monday, September 29, 2025 | Great Basin files Certificate Application under sections 7(b) and 7(c) of the Natural Gas Act |
Friday, July 18, 2025 | Great Basin provides revised draft RR to the FERC |
Monday, June 30, 2025 | FERC to comment on Revised Resource Reports |
Sunday, May 18, 2025 | Draft Applicant Prepared EA to be submitted to the FERC |
Wednesday, April 30, 2025 | Great Basin files Revised Resource Reports 1-13 to the FERC |